Paving US Highway 84, from the east end of the Monticello Bypass to the Jefferson Davis County Line, known as Federal Aid Project No. NH-0015-02(112)PH2 / 102062, in the County of Lawrence, State of Mississippi.
Project Completion: 348 Time Units
|
|
1  
|
|
|
|
|
|
2
|
Grading, drainage, and bridge work on US Highway 84 from Waynesboro to the Alabama State Line, known as Federal Aid Project No. NH-0015-03(006)PH3 / 102668, in the County of Wayne, State of Mississippi.
Project Completion: 338 Time Units
|
|
1  
|
|
|
|
|
|
3
|
Work necessary to renovate the truck scales at Osyka, known as Federal Aid Project No. IM-0055-01(076) / 102306, in the County of Pike, State of Mississippi.
Project Completion: 10/31/2007
|
|
|
|
|
|
|
|
4
|
Installation of communcation hubs on I-20, I-55, High Street, & West Street, known as Federal Aid Project No. NH-9999-00(331) / 103811, in the County of Hinds, State of Mississippi.
Project Completion: 5/30/2006
|
|
|
|
|
|
|
|
5
|
Overlaying approximately 9.6 miles of US Highway 61 from Clayton to just north of the five lane roadway, known as Federal Aid Project No. NH-0009-05(014) / 104505, in the County of Tunica, State of Mississippi.
Project Completion: 28 Time Units
|
|
1  
|
|
|
|
|
|
6
|
Replacing 4 bridges on Mississippi Highway 32 between Calhoun County Line and Mississippi Highway 15, known as Federal Aid Project No. BR-0051-04(008) / 100146, in the County of Chickasaw, State of Mississippi.
Project Completion: 368 Time Units
|
|
1  
|
|
|
|
|
|
7
|
Upgrading traffic signals on Mississippi Highway 42 through Petal, known as Federal Aid Project No. STP-0063-02(019)/103071, in the County of Forrest, State of Mississippi.
Project Completion: 120 Time Units
|
|
|
|
|
|
|
|
8
|
Upgrading drainage systems on Mississippi Highway 6, from Mississippi Highway 15 to Mississippi Highway 9, known as Federal Aid Project No. STP-0070-05(026) / 103956, in the County of Pontotoc, State of Mississippi.
Project Completion: 78 Time Units
|
|
1  
|
|
|
|
|
|
9
|
Work necessary to build a bike trail from Alcorn State University to the Natchez Trace, known as Federal Aid Project No. STP-0303-00(015) / 104245, in the Counties of Claiborne and Jefferson, State of Mississippi.
Project Completion: 51 Time Units
|
|
|
|
|
|
|
|
10
|
Overlaying US Highway 11/80 from Russell to west of Interstate 20/59, known as Federal Aid Project No. STP-1439-00(004) / 104351, in the County of Lauderdale, State of Mississippi.
Project Completion: 88 Time Units
|
|
|
|
|
|
|
|
11
|
Replacing one bridge on US Highway 80 at the railroad in Forest, known as Federal Aid Project No. BR-5525-00(005) / 100602, in the County of Scott, State of Mississippi.
Project Completion: 204 Time Units
|
|
1  
|
|
|
|
|
|
12
|
Installing high performance pavement markers on various routes throughout the District, known as Federal Aid Project No. STP-9999-06(004) / 103417, in District (6), State of Mississippi.
Project Completion: 127 Time Units
|
|
|
|
|
|
|
|
13
|
Overlaying Mississippi Highway 245 from Okolona to Shannon, known as Maintenance Project Nos. MP-1245-09(001) & MP-1245-41(001) / 302933, in the Counties of Chickasaw and Lee, State of Mississippi.
Project Completion: 99 Time Units
|
|
|
|
|
|
|
|
14
|
Overlayng Mississippi Highway 397 from the Kemper/Winston County Line north 9.38 miles, known as Maintenance Project No. MP-1397-80(005) / 302932, in the County of Winston, State of Mississippi.
Project Completion: 98 Time Units
|
|
|
|
|
|
|
|
15
|
Restriping various routes throughout District 2, known as Maintenance Project No. MP-2000-00(019) / 302919, In District (2), State of Mississippi.
Project Completion: 73 Time Units
|
|
1  
|
|
|
|
|
|
16
|
Overlaying US Highway 82 from Woodlawn Road to Leland, known as Maintenance Project No. MP-3082-76(013) / 302920, in the County of Washington, State of Mississippi.
Project Completion: 89 Time Units
|
|
|
|
|
|
|
|
17
|
Widening and overlaying US Highway 11 from Mississippi 590 to Laurel, known as Maintenance Project No. MP-6011-34(010) / 302934, in the County of Jones, State of Mississippi.
Project Completion: 62 Time Units
|
|
|
|
|
|
|
|
18
|
Placement of a single bituminous surface treatment on approximately 59 miles of various routes throughout District 7, known as Maintenance Project No. MP-7000-00(025) / 302881, in District 7, State of Mississippi.
Project Completion: 52 Time Units
|
|
|
|
|
|
|
|
19
|
Landscaping on Interstate 59, from Hillsdale to Black Creek, known as Federal Aid Project No. IM-0059-01(094) / 103393, in the Counties of Pearl River and Lamar, State of Mississippi.
Project Completion: 10/31/2006
|
|
|
|
|
|
|